Annual returns
Details of the annual return RET-100039395
Annual return status: | Completed |
Customer name: | BLIGH COAL LIMITED |
Annual return due date: | 01/04/2021 |
Reporting period: | 01/01/2020 - 31/12/2020 |
Permit reference: | EPPR00859613 |
Industry: | Minerals |
Condition Type: | Site-specific |
Permit holder(s): |
SUNGELA PTY LTD THUNGELA RESOURCES AUSTRALIA PTY LIMITED |
Activity | Location |
---|---|
Schedule 3 10 - Investigating the potential development of a mineral resource by large bulk sampling or constructing an exploratory shaft, adit or open pit |
MDL217: CENTRAL HIGHLANDS REGIONAL MDL218: CENTRAL HIGHLANDS REGIONAL |
Question | Answer |
---|---|
PRCP / no PRCP | A resource activity without an approved Progressive Rehabilitation and Closure Plan (PRCP) schedule – Only complete sections 1 and 3 of this form. |
Section 1 | |
1. Change may affect ERC decision? | No |
2. EA for eligible resource activity? | No |
3. EA for ineligible resource activity without approved PRCP schedule? | I/We have submitted GIS spatial information, which represents the onsite disturbance and rehabilitation within Table 1. Spatial information has been submitted via the department’s spatial information submission inbox - spatialsubmit@des.qld.gov.au. GIS spatial information has been prepared in accordance with the department’s Guideline - Spatial Information Submission (ESR/2018/4337), specifically Attachment 2 - Annual returns – shapefile attributes and submission requirements. I/We have provided a summary of the onsite disturbance and rehabilitation within Table 1. Yes |
4. EA for ineligible Resource Activity for CSG? | No |
Table 1. Area of disturbance / rehabilitation | |
Table 1 (1 Total Area ha) | 50594.0000 |
Table 1 (1 Spatial Submitted) | N/A |
Table 1 (2 Total Disturbance ha) | 0.0000 |
Table 1 (2 Spatial Submitted) | N/A |
Table 1 (3 Total Rehab Certified ha) | 14.6500 |
Table 1 (3 Spatial Submitted) | N/A |
Table 1 (4 Total Rehab Completed ha) | 0.0000 |
Table 1 (4 Spatial Submitted) | N/A |
Table 1 (5 Total Rehab Commenced ha) | 0.0000 |
Table 1 (5 Spatial Submitted) | N/A |
Table 1 (6 Area Disturbed ha) | 0.0000 |
Table 1 (6 Spatial Submitted) | N/A |
Table 1 (7 Approved Progressive Certification ha) | 3.2900 |
Table 1 (7 Spatial Submitted) | N/A |
Table 1 (8 Rehab not yet Approved ha) | 0.0000 |
Table 1 (8 Spatial Submitted) | N/A |
Table 1 (9 Rehab Commenced ha) | 0.0000 |
Table 1 (9 Spatial Submitted) | N/A |
Table 1 (10 Proposed Disturbance ha) | 0.0000 |
Table 1 (10 Spatial Submitted) | N/A |
Table 1 (11 Rehab for Certification ha) | 0.9900 |
Table 1 (11 Spatial Submitted) | Yes |
Table 1 (12 Rehab not for Certification ha) | 0.0000 |
Table 1 (12 Spatial Submitted) | N/A |
Table 1 (13 Rehab to Commence ha) | 0.0000 |
Table 1 (13 Spatial Submitted) | N/A |
Section 2 | |
5. Has there been a change to the carrying out of the resource activity that may affect the estimated rehabilitation cost (ERC) decision for the activity? | |
6. Has the required GIS Spatial information been submitted in accordance with an approved PRC Plan? | |
7. Have you complied with your PRCP schedule? | |
8. Have you complied with all other conditions imposed on the PRCP schedule? | |
9. Are works related to any other rehabilitation or management milestones underway? | |
Table 2. Area of disturbance / rehabilitation / improvement (PRCP) | |
Table 2 (1 Total Area ha) | |
Table 2 (1 Spatial Submitted) | |
Table 2 (2 Total Disturbance ha) | |
Table 2 (2 Spatial Submitted) | |
Table 2 (3 Total Rehab Certified ha) | |
Table 2 (3 Spatial Submitted) | |
Table 2 (4 Total Rehab Completed ha) | |
Table 2 (4 Spatial Submitted) | |
Table 2 (5 Total Rehab Commenced ha) | |
Table 2 (5 Spatial Submitted) | |
Table 2 (6 Total Sufficient Improvement ha) | |
Table 2 (6 Spatial Submitted) | |
Table 2 (7 Total Improvement Commenced ha) | |
Table 2 (7 Spatial Submitted) | |
Table 2 (8 Area Disturbed ha) | |
Table 2 (8 Spatial Submitted) | |
Table 2 (9 Approved Progressive Certification ha) | |
Table 2 (9 Spatial Submitted) | |
Table 2 (10 Rehab not yet Approved ha) | |
Table 2 (10 Spatial Submitted) | |
Table 2 (11 Rehab Commenced ha) | |
Table 2 (11 Spatial Submitted) | |
Table 2 (12 Sufficient Improvement ha) | |
Table 2 (12 Spatial Submitted) | |
Table 2 (13 Improvement Commenced ha) | |
Table 2 (13 Spatial Submitted) | |
Table 2 (14 Proposed Disturbance ha) | |
Table 2 (14 Spatial Submitted) | |
Table 2 (15 Rehab for Certification ha) | |
Table 2 (15 Spatial Submitted) | |
Table 2 (16 Rehab not for Certification ha) | |
Table 2 (16 Spatial Submitted) | |
Table 2 (17 Rehab to Commence ha) | |
Table 2 (17 Spatial Submitted) | |
Table 2 (18 Proposed Sufficient Improvement ha) | |
Table 2 (18 Spatial Submitted) | |
Table 2 (19 Improvement to Commence ha) | |
Table 2 (19 Spatial Submitted) | |
Section 3 | |
Signatory Name | Shane Wright |
Signatory Position | Executive General Manager Operations and Development |
Date | 11/03/2021 |
Related documents
Document title | Document link |
---|---|
RET-100039395 | view document (Opens in new window) |
Related environmental authorities
To view other information holdings which may be related to the Environmental Authority, select the associated permit number below.
Permit number | Status | Effective date |
---|---|---|
EPPR00859613 | Granted | 11/02/2013 |